PROJECT eight
Katoomba.
Location:
katoomba
completion year:
2023
sector:
insurance claim
The project at Katoomba involved rectification works following a landslide that impacted a residential property. We initiated the stabilisation process through detailed geotechnical interventions.
Key activities included:
Drilling and assessment of rock underpinning bolts (anchors) on site to ensure their effective extension and secure socketing into suitable bedrock.
Verification that all inspected rock bolts met the designed serviceability and end bearing capacity as per the specifications outlined in Section 2 of the project report.
Continuous monitoring and evaluation based on onsite observations and provided information, to ensure adherence to the structural engineer's requirements.
Installation of HDGAL N25 permanent rock anchors
Strip drainage cells and SL81 mesh
Finished with a natural stone rock mock finish